Top Data Center Power Planning Considerations

windchill features best plm software
Written by SPK Blog Post
Published on November 10, 2011

Our Infrastructure Management Services include data center migration planning and deployment. Recently, I moved two different companies to new facilities. Both had drastically different IT needs. One was heavier on infrastructure and server room. The other was not focused so much on infrastructure as it was on phones and vendor services. For the first company, we needed to plan the data center carefully to ensure a smooth operation once we moved. One of the challenges was power. Below is some information about things to think about in your next move.  Let me know if you have other opinions or experiences.

Data Center Power Plan for a New Site

Before anything, determine the service level agreement you need to meet.  Most Data Centers fall
into three categories:

1.  HA – typically a Collocation facility.  This is where you need fully redundant N+1 power,
network, and cooling for applications that are always up.
2.  Corporate critical daytime but available for scheduled maintenance evenings or
weekends.  Some potential outages may occur for unexpected hardware failures but
critical infrastructure is redundant.
3.  Engineering Data Center.   Desired to be up but no one is willing to pay to create a higher
availability with redundant architecture.

In this case, we’ll focus on …

Download the Full document here.

Latest White Papers

Accelerating Product Development the SPK Way

Accelerating Product Development the SPK Way

Developing high-quality products quickly can be a challenge without the proper tools, processes, and partners to help. Dive into this eBook to discover how partnering with SPK can help you achieve product development success.What You Will Learn In this eBook, we will...

Related Resources

Transitioning Your Engineering Calculations to Mathcad Prime 11

Transitioning Your Engineering Calculations to Mathcad Prime 11

As the world of engineering continues to evolve, so does the need for more sophisticated tools to manage complex calculations and data.  The end-of-sale of Mathcad 15 and Mathcad Prime 1.0-6.0 marks a significant shift, as PTC moves forward with its latest offering,...

Highlights and Key Insights from Atlassian Team ’25

Highlights and Key Insights from Atlassian Team ’25

Atlassian Team '25, the premier event for Atlassian enthusiasts, partners, and users, showcases the latest innovations and strategies designed to enhance collaboration and efficiency across teams globally.  This year’s event, held in Anaheim, CA, brought together...